For years, a network crew needing 50 or 100 trefoil cleats for a substation job could get them off the shelf within days. That’s no longer a given. Utility-scale batteries use the same cable management hardware as substations, and they use it in volumes no distribution job comes close to. When a six-week outage meets a 14-week lead time, the pressure is to fit whatever is available. Here’s what to check before you do.
From Shelf Item to 14 Weeks
Battery sites run the same single-core cable arrangements as substations: cable runs from power conversion systems to step-up transformers, and collector cables to the site substation. A single site repeats those runs dozens of times, so one project can order cleats, clamps, glands and straps in the thousands.
That demand is global. Battery projects are being built at scale around the world, and in Identimark’s experience, the largest markets, led by the United States, are absorbing much of the manufacturing capacity for cable management hardware. When overseas manufacturers prioritise larger, higher-value orders, Australian and New Zealand buyers can find themselves further down the queue.
On one recent Australian battery project, a delivery agreement with another supplier for 12,000 trefoil cleats, clamps and cable glands slipped by three months, as that supplier’s overseas manufacturer continued to prioritise shipments to the US. To hold the program, the EPC paid a significant unplanned air freight bill to get the product to site on time.